Thursday, June 16, 2011

Update for Thursday

First coat on the walls on the East building is near completion. Twenty per cent of the middle building has received first coat. We will start painting roll-up doors on the first two buildings tomorrow. The colour has not been approved for the windows, so we are holding off.

Greg
Operations